#3445: Infrastructure Migration 2025
-------------------------------------+---------------------------
Reporter: strk | Owner: sac-tickets@…
Type: task | Status: new
Priority: critical | Milestone:
Component: SysAdmin/Infrastructure | Keywords:
-------------------------------------+---------------------------
[ Due: before end of 2025 ]
As discussed around august 2025 with Lance from OSUOSL we need to get our
servers ready for migration to a new data center and get rid of old
servers we no longer need.
What we had decided to do was this:
1. Containerize osgeo6 on osgeo9
2. Shutdown osgeo5 (aka backup.osgeo.osuosl.org)
3. Get new discs for osgeo6 server and reformat it to be an lxd (or incus)
host
4. Move osgeo3 containers somewhere else (#3408)
5. Decide what to do with osgeo4 ?
--
Ticket URL: <Making sure you're not a bot!;
OSGeo <Gter - OSGeo;
OSGeo committee and general foundation issue tracker.