What work was completed during the said period?
- Implemented unit tests for meta sql functionality[1][2].
- Consolidated all the code and committed the changes[3].
- Refactored existing codebase.
What do I plan to do the next week?
- Continue refining and expanding unit tests for remaining files.
- Write detailed documentation to reflect changes done so far.
Am I blocked on anything?
No, currently I am not blocked on anything.
Links:
[1]https://github.com/dhruvmehtaaa/ZOO-Project/blob/main/zoo-project/zoo-kernel/meta_sql.c
[2]https://drive.google.com/file/d/1oyy8uWZP0QSBsbeN1GEgg7R8s35qSm3V/view?usp=sharing
[3]https://github.com/dhruvmehtaaa/ZOO-Project/tree/Week-11/testing/unit_tests