GSoC-2025 - First 2 weeks Report: Web Administration Interface for istSOS

Name : Luca Abate
Project Title : Web Administration Interface for istSOS
Mentors : Massimiliano Cannata, Daniele Strigaro, Claudio Primeano
Organization : OSGeo / istSOS
OSGeo Profile : OSGoe Profile Link
Project Wiki : Github Wiki Link
Repository : Repo Link


What I have done during the first 2 weeks of coding period (June 2 - June 15)

1. Linked backend to my interface
2. Data fetch functions
3. Created a page for each db's table
4. Added a Leaflet map that shows every 'thing' element
5. Implemented authentication


Plan for Next Week (June 16 - June 22)

During this week and the next, I will be taking a total of five exams at SUPSI. Therefore, in agreement with my mentors, the workload has been reduced. We will use this time to engage with real users of the istSOS service in order to gather as much information as possible to create a more complete and user-friendly interface.

Am I blocked on anything?

No, I am not currently blocked on anything.