Original Plan (from Proposal):

  • Implement basic driver to connect SQL and C++
  • Create data pipeline from SQL input to graph representation

What I got done:

  • Resolved all compilation errors.
  • Fixed parameters and data types according to Boost implementation.
  • Resolve all the merge conflicts.

Project Engagement:

  • Attended weekly project meetings on June 16th 2025.
  • Attended a meeting this week to have some clarity on merge conflicts on June 20th 2025.
  • Collaborated with mentors on reviews , feedback and merge conflicts.

Links to Work Done:

  • Final Pull Request : #454
  • Tried Pull Request : #453 , #450
  • Updated Wiki Page : wiki

Plan for Next Week (June 16 – June 22) :

  • Focus on starting the testing process.

Blockers:

None