GSoC 2025 Week 5 Report: Implementing Sloan Ordering Algorithm to pgRouting

Progress Report for Week 5 (June 30 – July 06)

Original Plan (from Proposal):

  • Create comprehensive test cases
  • Begin performance optimization

What I got done:

  • Fix input parameters in SQL file.
  • Create the initial files of the documentation queries.
  • Fix the intial pgTap test file.
  • Adjust build configuration files to include new and updated source and documentation files.
  • Refactor function signatures and parameter types, replacing custom tuple types with int64_t arrays.
  • Remove extra whitespace and corrected function signature in comments.
  • Simplify result tuple logic and removed unused helper and type includes.
  • Minor formatting and include adjustments; no logic changes.

Project Engagement:

  • Attended weekly project meetings on June 30th 2025.
  • Collaborated with mentors on code review feedback and project direction

Links to Work Done:

Plan for Next Week (July 7 – July 13):

Implement error handling and edge cases
Midpoint code review with mentors

Blockers:

None

Best regards,
Bipasha Gayary