Hello everyone,
This is my report for Week 3 of the GSoC coding period, in which I enlist the tasks I fulfilled during the week.
Any feedback, comments, and suggestions are welcome.
Weekly Report (June 16th - June 22nd)
I performed the following tasks during this week:
-
Set up a new development environment on Ubuntu Linux and configured the required tools for project development.
-
Reviewed the finalized as_of mockup and mapped the proposed workflow to the existing istSOS user interface.
-
Started the implementation of the as_of functionality in the frontend.
-
Developed the initial UI component corresponding to the first stage of the proposed three-step as_of workflow.
-
Explored the relevant frontend codebase and component structure to understand how the new functionality can be integrated while remaining consistent with the existing interface.
-
Continued documenting implementation considerations and identifying the remaining tasks required to complete the as_of user flow.
What do I plan to do next week?
-
Continue the implementation of the remaining components required for the as_of workflow.
-
Integrate the individual UI components into a complete user flow based on the approved mockup.
-
Discuss the current implementation progress and receive feedback during the mentor meeting scheduled for June 29th.
-
Refine the implementation based on mentor suggestions and prepare the work for submission as a pull request.
-
Resume work on the from_to functionality and continue exploring design approaches based on previous discussions and feedback.
Am I blocked on anything?
- No, currently I do not have any blocking issues.
--