Hi everyone,
The following is my tenth weekly report (Jul 31 - Aug 6):
- What did I get done this week?
-
Now tests pgTap passes for v3.1.3.
-
Created a tag on my forked repo[1].
-
Update test passes. Latest can be [2] and previous on [3].
- What do I plan on doing next week? -
Start preparing PR to main repository.
- Am I blocked on anything? -
No.
PR of this week can be found in [4].
The wiki page with the weekly report can be found in [5].
The repository can be found in [6].
Any feedback, comments, and suggestions are welcome.
Best regards,
Abhinav Jain
[1] https://github.com/AbhinJ/GSoC-pgRouting/releases/tag/abhinav-aug6-tag1
[2] https://github.com/AbhinJ/GSoC-pgRouting/actions/runs/5772131687
[3] https://github.com/pgRouting/GSoC-pgRouting/actions/runs/5647360212
[4] https://github.com/pgRouting/GSoC-pgRouting/pull/337
[5] https://github.com/pgRouting/pgrouting/wiki/GSoC-2023-Implement-pgr_withPointsKSP-and-Add-Overloads