I wanted to let you know about the work I completed during the 11th week, from Aug 7th to Aug 13th.
- The work I did in this week:
- [doc] changes suggested by @cvvergara.
- [KSP] changes suggested by @cvvergara.
Link to the Pull Request: [1]
- My plans for next week:
- Work on rebasing.
- Am I blocked on anything?
I currently do not have any blocking issues and can proceed with my tasks smoothly.