I am writing this email to update you on the work I completed during the fifth week, which spanned from June 26th to July 2nd.

  • The work I did in this week:
  • Bug fixes in output columns
  • Some testing with doc queries

Link to the Pull Request: [1]

  • My plans for next week:
  • Catch up on my week 5 work.
  • Will start working on documentation.
  • pgtap test cases
  • Am I blocked on anything?
    I currently do not have any blocking issues and can proceed with my tasks smoothly.